Rooppur Nuclear Plant Plans First Fission Reaction Tonight

Rooppur Nuclear Plant Plans First Fission Reaction Tonight
Rooppur Nuclear Plant Plans First Fission Reaction Tonight
Last updated: 10/11/2026 3:50:00 PM

Bangladesh’s Rooppur Nuclear Power Plant in Ishwardi, Pabna, is scheduled to begin a controlled nuclear fission reaction in its first unit on Sunday night (October 11), marking a major step towards electricity generation. The Bangladesh Atomic Energy Regulatory Authority (BAERA) has approved the start of the process.

Project sources said the approval was granted on October 8. Known as “first criticality,” the process involves initiating a controlled nuclear chain reaction at low power. Engineers will test the reactor’s safety systems, control mechanisms and other technical equipment before gradually increasing its power.

The next stages will include testing the turbine and generator systems and preparing to connect the unit to the national grid. Trial electricity supply could begin after successful testing and the necessary regulatory approvals. The process may take seven to eight months, according to project officials.

Project Director Dr Md Kabir Hossain said, “We are moving forward with plans to begin the fission reaction on Sunday night.” BAERA Chairman Mahmudul Hasan said the approval was granted after reviewing safety-related matters. Two further approvals from the regulator will be required before the plant can supply electricity to the national grid.

Project officials expect the first unit to supply around 300 megawatts of electricity by late December, provided preparations and tests proceed as planned. However, the timeline will depend on technical assessments and further approvals.

Each of Rooppur’s two units has a generation capacity of 1,200 megawatts, giving the plant a combined capacity of 2,400 megawatts once both units are operational. The first shipment of uranium fuel for the second unit arrived at the project site on October 3, while fuel loading in the first unit began in May this year.

 

Russia’s state nuclear corporation Rosatom is providing technical assistance, while the Bangladesh Atomic Energy Commission is implementing the project under the Ministry of Science and Technology.

On January 25, 2026, the Executive Committee of the National Economic Council approved a revised project cost of Tk 138,685 crore and extended the deadline to June 2028. Around 90 per cent of the project’s financing comes from Russian loans.

Give Your Feedback/Opinion

Conditions:
You cannot use abusive words/sentences. You can't sneer at anyone. You cannot give aggressive statement to anyone.

Most Read
Most Discussed
Public opinion polls

More Capital (রাজধানী)